When you’re building your first home, two dates matter most: the day you move in, and the days the money goes out.
Building a house with Robinson & Fuller Homes takes around 12 weeks of design, site surveys and council approval before construction, then typically about 22 weeks once construction starts. You don’t pay a deposit, and nothing is paid until your slab is poured.
If you’re a first home buyer trying to plan around a lease ending or a baby arriving, knowing how long it takes to build a house helps you plan everything else. The timings below are typical, and your design, council and the weather can all move them. We’ll give you a detailed schedule for your own build.
The short version
- Your start date depends on approvals, selections and your bank’s commencement letter.
- Four progress payments, at slab, frame, lock-up and fixing.
- Your bank still wants a deposit for your loan, and federal schemes can lower it.
Jump to:
- The timeline
- The stages of a build
- When you pay
- How a construction loan works
- When your build will start
How long does it take to build a house in Dubbo?
With Robinson & Fuller Homes, a typical build takes around 12 weeks of preparation before construction and about 22 weeks of construction after that. Design and council can stretch the first part, and wet weather the second.
Design, surveys and council approval: around 12 weeks
Before anyone breaks ground, your plan is finalised, the block is surveyed, the slab is designed and your plans go to council. Robinson & Fuller Homes handles the council submission for you, and approval typically takes four to six weeks of that time. If you’re having a custom plan drawn, the drafting takes about two weeks.
Construction: typically about 22 weeks
Once construction starts, Robinson & Fuller Homes typically completes a home in about 22 weeks. You’ll get regular progress updates and photos along the way, and you can book site visits with your supervisor.
What can stretch the timeline
Some builds take longer than the typical figures. A complex custom design takes longer to draw and approve. Some councils ask for more information. Long spells of wet weather stop work on site. Changes you make after construction starts can also add time.
What are the stages of building a house?
A house goes up in four main stages: slab, frame, lock-up and fixing. Each one is a milestone you, your builder and your bank can all see.
The stages at a glance
| Stage | What happens |
|---|---|
| Slab | The site is prepared and the concrete slab is poured |
| Frame | The wall and roof frames go up |
| Lock-up | The roof, external walls, windows and external doors are on, so the house can be locked |
| Fixing | Internal linings, cabinetry, internal doors and trims go in |
What the fixing stage is
The fixing stage of a house build is when the inside starts to look like a home. Plasterboard is up, and the kitchen, vanities, internal doors, skirting and architraves go in. Robinson & Fuller Homes recently added fixing as its own payment stage to spread the payments more evenly.
Pick your selections before construction starts
Your paint colours, tiles, benchtops, flooring, fixtures and kitchen all have to be chosen before Robinson & Fuller Homes can start. Michael Fuller, licensed builder at Robinson & Fuller Homes, says first timers can feel anxious choosing so many things without seeing how they’ll come together. That’s normal, and the team walks you through it.
When do you pay the builder?
You pay Robinson & Fuller Homes in stages as the build progresses, starting once the slab is poured.
No deposit, nothing until the slab is poured
The design, quote and approvals all happen before you pay Robinson & Fuller Homes anything.
The progress payment schedule
A progress payment schedule sets out what you pay at each stage of the build. Robinson & Fuller Homes takes 15% at slab, 25% at frame, 25% at lock-up and 15% at fixing complete. You only pay for each stage once that stage is done.
Why we wait for a commencement letter from your bank
Robinson & Fuller Homes waits for a commencement letter from your bank so no build starts while there’s still doubt about the money. The letter confirms your finance is approved.
How does a construction loan work?
A construction loan pays your builder in stages as your house goes up, then usually switches to a standard home loan once it’s finished.
Drawing down in stages
Each time your builder reaches a stage, they send an invoice, you sign it off, and your bank pays it from your loan. While the loan is being drawn, CommBank, for example, says it charges interest only on the amount drawn down, so your repayments start small and grow as the house goes up.
How much deposit the bank still needs
Your bank will want a deposit for your construction loan. Michael says saving that deposit is the real hurdle for first home buyers, rather than paying the builder. The 5% Deposit Scheme and Help to Buy can lower how much you need.
When the $10,000 grant lands on a build
If you’re eligible for the First Home Owner Grant, your bank can lodge the application so the $10,000 goes towards your first progress payment. Revenue NSW sets out how to apply.
When will your build start?
Your build starts once your plans are approved, your selections are made and your bank has confirmed your finance.
Why start dates worry first home buyers
Michael says a lot of first home buyers are anxious about when their build will start. Many have heard stories of builds promised for one date that kept slipping. Our guide to choosing a builder covers what to ask about start dates before you sign. If you’ve bought land that’s still waiting on registration, our guide to buying land to build a house explains how that timing works.
How we schedule your build
Michael plans his schedule carefully and tells clients the real start date up front, even if that date is months away. If the earliest he can start is April next year, he says so. Knowing the real date means you can plan around it instead of waiting on one that keeps moving.
Planning your move? Ask us for a realistic start date for your build.
Frequently asked questions
Is there a limit on how much deposit a builder can take in NSW?
Yes. Under the NSW Home Building Act, a builder can’t ask for more than a 10% deposit on a residential building contract.
What happens if it rains for weeks?
It can push your finish date out. Your contract sets out how weather delays are handled, and your supervisor will tell you if the schedule moves.
Can I make changes once construction starts?
Some changes are possible, but they can add cost and time, and some need council approval. If something changes, talk to us as early as you can.
Can I use my own tradespeople for part of the build?
Sometimes. Robinson & Fuller Homes will consider it case by case, as long as they meet our licensing, insurance and quality standards, and it’s agreed before the contract is signed.
Get a Real Start Date for Your Build
A timeline only helps if it’s honest. Robinson & Fuller Homes will walk you through each stage of your build, tell you when each payment falls due, and give you a start date you can plan your life around.
Call (02) 6882 7444, request a free quote, or read more about our building process. If you’re still working out your budget, our guide to what it costs to build a house in Dubbo is a good place to start.
Written by the team at Robinson & Fuller Homes.
Disclaimer: This article is general information only. Timeframes are typical, and your building contract sets out the schedule and payments for your build.